How things have changed: smoothing out the wrinkles in Gateway 2

Tuesday 27 January 2026

Stevan Tennant

Managing Director Development
Ballymore

After early Gateway 2 applications faced long delays, Ballymore’s Stevan Tennant shares how the process is improving. With clearer guidance and greater consistency from the Building Safety Regulator, approval times have dropped dramatically, signalling renewed confidence for high-rise delivery.

 
In February 2024, Ballymore submitted its first Gateway 2 application to the Building Safety Regulator (BSR). At the time, we were cautious about how long the process might take, but confident nonetheless, given our long track record in delivering high-rise buildings, and the capability of our multi-disciplinary design team.
Little did we know the approval process would take a slow and painful 65 weeks.

We were not alone. The uncertainty around approval timescales sent shockwaves through the industry, contributing to historically low levels of new home starts, while investors and developers began exiting the high-risk building market. The shift has been so fundamental that funders now require Gateway 2 approval before deploying capital - planning consent is no longer the major milestone it once was.

Fast forward two years and, to the BSR’s credit, much has changed. Our most recent application was approved in just 63 days, including the statutory fire approval period.

So what changed? For a start, we learned a great deal - both directly and through extensive industry engagement. Meetings, conferences and roundtables have all played their part. The BSR has also evolved. There has been no reduction in rigour or compromise, but there is now far greater consistency, focus and clarity. The new leadership at the BSR has been transformational and offers real grounds for renewed optimism.

Information requests are clearer and more proportionate. Gone are the questions about future skirting board colour choices or lift signage, replaced by a genuine focus on enabling delivery and driving projects forward.

Staged Gateway 2 applications are also encouraging and could help narrow the gap between planning and site start. This is particularly important while the time and cost differential between high-risk and non-high-risk buildings remains a significant barrier to bringing forward new high-density schemes.

Gateway 3 remains a concern - and a challenge for another day - but for now, let’s take the win and recognise the progress that’s been made.


Stevan Tennant

Managing Director Development
Ballymore



Recent

Five minutes with... Rick Gray

News

Five minutes with... Rick Gray

David Taylor meets Cumming Group’s Rick Gray to discuss the firm’s ambitions, AI, recovery in residential and hospitalit...

Lord Foster to speak at the NLA Awards 2026

News

Lord Foster to speak at the NLA Awards 2026

Lord Foster will join us at Guildhall on 19 November to receive the NLA Londoner of the Year 2026 award and give a speec...

How developers and registered providers can unlock London’s stalled affordable homes

News

How developers and registered providers can unlock London’s stalled affordable homes

Insights from the LGL x NLA roundtable on how earlier collaboration, shared risk and stronger partnerships can help unlo...

Stay in touch

Upgrade your plan

Choose the right membership for your business

Billing type:
All prices exclude VAT

Small Business Membership

Medium Business Membership

Large Business Membership

View options for Personal membership